Delay :-(

Unfortunately I heard yesterday that Cheshire East council have refused permission for the traffic management required near the Parkfield road cabinet to allow the fibre run to be completed. This is due to an ‘embargo’ on any roadworks over the Christmas period. Openteach tried, in vain, to appeal against this decision.

This work will now be put back until January 8th, which means we’ll miss the November switch on.

Sorry to be the bearer of bad news, I’m currently pushing for Openreach to give me a new date and will provide a further update once I know more.

 

Advertisements

Almost there…

Lots of activity happening in the next couple of weeks, and you’ll likely see a number of traffic lights up along the Chelford road.

There are two main stretches that are being worked on – the main run from the Booths Hall roundabout to the end of School Lane is happening next week – this is more proving and sub-ducting getting the route ready for the fibre connection.

Next Sunday (19th) will see traffic lights up near Parkgate road where they will be working on the section from the section of road from the Knutsford cabinet.

Connecting the existing copper telephone lines to our new cabinet is also happening next week. Power to the cabinet is due to complete by 27th Nov traffic management will be in place from the 20th to allow this work to complete.

Provided there are no major blockages on the route, work should complete on the 28th November. Service Providers should be notified a few days later, and we’ll then be able to order a fibre service from the broadband provider of your choice.

Watch this space, and fingers crossed there are no setbacks. I’m getting a guided tour on-site from the deployment team next week so I’ll be able to post more detail then.

Dave

Our Cabinet has Landed…Amber Warning

As you may have seen, our new cabinet has now been installed at the end of School Lane, which is the first major milestone in the build out . The next steps are to run the fibre from Knutsford, install power and connect the existing existing copper lines to the cabinet.

img_5382.jpg

I’ve been on the phone to BT today to get an update on progress. Whilst investigating the fibre run, they have found a blockage that they need to remove in the existing ducting (Despite asking, I still don’t know why this took a year to get to this point).

This will require temporary traffic lights on the Chelford road to allow them to fix the issue, for which they need to apply for a permit. We are awaiting an outcome on the application and to find out how long this process will take. There’s a chance this will delay the switch on date, but I’ll keep on at BT and will provide another update once I find out specifics.

As a result, I’ll put the project on an ‘Amber’ warning the November switch on date. We might still make it, but there’s a few unknowns we need to get resolved. Watch this space.

5651905_orig

Works Update

I have had a few enquires on the works to bring fibre broadband to Ollerton. The good news is that we remain on track for a November “switch on”.

The next milestone is to install the cabinet at the Chelford Road end of School lane. We should see happen in the next few weeks. In addition, BT are checking the cable routing making sure it is clear of any obstructions / blockages such as tree roots and silt. Any blockages may introduce some delays to the process, but we should get clarity on this shortly. Fingers crossed.

So Far, So Good…

Just a quick update on the fibre install works…everything is seemingly on track for a November 2017 “switch on” date.

Here’s a short version of the update I’ve received from BT today:

  • ‘First stage’ plans have been drawn up and completed.
  • Works have been issued to survey the fibre routes determined by those plans.
  • The works will retest ‘on the ground conditions’ including routes, presence of other plant, fibre joints, routes available as expected and network integrity.
  • The work has been ongoing since April.   That work is completing.  This is running to plan. No delays are currently expected.
  • We are on track for November.

 

Green Light!

I’ve been in conversations with BT and we have found a way to submit all the remaining funding requests. I now have assurance from BT that the scheme will be fully funded by the voucher scheme.

As a result I have now signed the contract with BT and the project is now officially up and running.

We have a target date of November 2017 to bring the service live. I’ll provide updates throughout the year as we progress throughout the project.

After 11 months of getting this scheme off the ground, we’re finally looking like this is going to happen…

Thanks all for your ongoing support.

Dave

Apply for Government Funding!

***Update – if you have already applied for funding, then there is nothing for you to do***

You may remember the satellite voucher scheme that was reported in the press earlier in the year.  Every household receiving under 2mbps is eligible for £350 towards the cost of a satellite installation cost. At the time we discounted this as a solution –  Satellite is a sub-standard connection and the monthly costs (on top of the existing line rental) were about £30 per month and capped at a fairly stingy 10 gbit. Not a viable solution.

I  have been in regular dialog with BDUK and Connecting Cheshire to persuade them to make our community scheme eligible for this funding. In parallel I negotiated a discount on our scheme from £35,000 to around £20,000. BT also put pressure on BDUK to allow community self-funded schemes to be eligible for this funding.

 

We are one of (if not the) first community fibre scheme in the country to be eligible for the voucher scheme money. It means we can run our own project as planned. Also the number of eligible households (around 70)  covers the total cost of the works.

 

I have incorporated a Community Interest Company “Connecting Ollerton”  that will contract with BT to get the works done once we secure the funding.

 

This is where you come in. To fund it, we need every household to register for the voucher scheme as soon as possible. You can do it  HERE  just click the link, fill out the form and your £350 voucher will go towards the scheme. When inputting the email address, please enter my email address david@malkinson.co.uk so I can collect all the codes, and send them off to BDUK and keep track of who has and hasn’t completed it.

 

Instructions for filling in the form:

 

 – On the first page, please make sure you fill in your full name, and enter my email address (david@malkinson.co.uk) Don’t worry if you put in your email address, it will still go through OK.
– Answer No to the question  “Do you already have a Satellite broadband product at this address?”
– Answer No to the question  “Is Superfast Broadband available from any other supplier at this address? “
– Answer No to the question  “Does BT already provide an Internet service >2Mbps to this address?
– Answer Yes to the question  “I understand the limitations of basic broadband, and I am happy to proceed with the application”

Ready to Receive Pledges

Connecting Ollerton is now ready to receive pledges.

If you are interested in supporting the project, then please fill out this short form.

The deadline to receive all pledges is Friday 12th February. After that date (and hopefully sooner) we’ll know if the project has the support it needs to go ahead.
Before pledging, please have a look at the map on this page to see if you are eligible for the scheme. If you received a leaflet through your door before Christmas then your household will qualify for the scheme.
Cllr Neil Hanlon and Mike Brown will be distributing leaflets to the remaining houses in Ollerton this weekend to garner support for a wider programme of works. Good luck Neil and Mike
For me, this is most exciting part of the project so far, and we’ll find out if the work put in will actually bear fruit….of course I have every confidence we’ll race over the finish line!
Dave

Press Attention, Get Ready to Pledge

Lots going on this week…

Firstly, the Knutsford Guardian have been in contact and have run an article on our scheme. You can find it here (I’m the one holding the laptop for no discernible reason)

This week, I will be putting together a platform to enable us to receive everyone’s contributions to the scheme. I should have something to show in a few days. I’d like to get the pledges in as quickly as possible, so please have a think about your potential contribution if you haven’t already.

Dave